Assessment Year | 2018 |
---|---|
Principal Product | Milk |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
92,000
ft2
|
Annual Production | 60,480
units
|
Production Hrs. Annual | 8,640
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $273,154 | 7,236,240 |
kWh
|
$0.038 | |
Electricity Demand | $243,413 | 18,708 |
kW-mo/yr
|
$13.01 | |
Electricity Fees | $105,560 | - |
|
- | |
Natural Gas | $438,382 | 70,050 |
MMBtu
|
$6.26 | |
Waste Disposal Costs | |||||
Water Usage | $135,420 | 54,540 |
Tgal
|
$2.48 | |
TOTAL YEARLY COSTS | $1,195,929 | ||||
RECOMMENDED SAVINGS* | $382,100 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $375,599 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8113: Purchase gas directly from a contract gas supplier | $242,000 | $1,000 | - | - | - | - | $242,000 | |
02 | 2.8121: Apply for tax-free status for energy purchases | $76,380 | $1,000 | - | - | - | - | $76,380 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,471 | $39,272 |
$13,743
361,665
kWh
|
$6,445
-
kW-mo/yr
|
$4,283 | - | - | |
04 | 2.7135: Install occupancy sensors | $17,732 | $2,030 |
$6,576
173,047
kWh
|
$7,759
-
kW-mo/yr
|
$3,398 | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,477 | $150 |
$6,459
169,982
kWh
|
$3,046
-
kW-mo/yr
|
$972 | - | - | |
06 | 2.2511: Insulate bare equipment | $6,501 | $2,665 | - | - | - |
$6,501
-
MMBtu
|
- | |
07 | 2.7495: Install replacement doors | $4,539 | $300 |
$4,539
119,458
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $382,100 | $46,417 |
$31,318
824,152
kWh
|
$17,249
-
kW-mo/yr
|
$8,653 |
$6,501
-
MMBtu
|
$318,380 | ||
TOTAL IMPLEMENTED | $375,599 | $43,752 |
$31,318
824,152
kWh
|
$17,249
-
kW-mo/yr
|
$8,653 | - | $318,380 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs