ITAC Assessment: UU0125
ITAC logo
ITAC Assessment: UU0125
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Carbon Fiber, Synthetic Resins, Prepreg Material
NAICS 335991: Carbon and Graphite Product Manufacturing
SIC 2824: Manmade Organic Fibers, Except Cellulosic
Sales Range $100
M
to 500
M
# of Employees 423
Plant Area 200,000
ft2
Annual Production 3,250,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $910,959 27,854,237
kWh
Electricity Demand $41,677 3,571
kW-mo/yr
Electricity Fees $282,474 -
Natural Gas $401,529 135,797
MMBtu
Waste Disposal Costs
Water Usage $45,504 38,700
Tgal
Water Disposal $29,134 10,368
Tgal
Other Liquid (non-haz) $314,165 72,455
gal
Other Liquid (haz) $464,948 116,070
gal
Solid Waste (non-haz) $30,460 906,000
lb
Gaseous Waste $71 101,712,096
lb
TOTAL YEARLY COSTS $2,520,921
RECOMMENDED SAVINGS* $71,175 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,156

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings Solid Waste (non-haz) Savings
01 2.1321: Replace fossil fuel equipment with electrical equipment $32,802 - $25,275
772,929
kWh
$13,562
-
kW-mo/yr
$2,581 $(-8,615.3)
-
MMBtu
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $9,851 $18,588 $6,227
190,456
kWh
$3,624
-
kW-mo/yr
- - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $7,110 $20 $3,778
115,536
kWh
$2,799
-
kW-mo/yr
$533 - - -
04 3.5311: Recover and reuse waste material $6,187 $3,150 - - - - - $6,187
-
lb
05 2.2622: Replace existing chiller with high efficiency model $5,417 $39,198 $1,459
44,208
kWh
$3,958
-
kW-mo/yr
- - - -
06 2.7135: Install occupancy sensors $4,418 $7,220 $4,418
135,121
kWh
- - - - -
07 3.4151: Minimize water usage $3,700 $200 - - - - $3,700
-
Tgal
-
08 2.7224: Reduce space conditioning during non-working hours $1,690 - $268
8,186
kWh
- - $1,422
-
MMBtu
- -
TOTAL RECOMMENDED $71,175 $68,376 $41,424
1,266,436
kWh
$23,943
-
kW-mo/yr
$3,114 $(-7,192.9)
-
MMBtu
$3,700
-
Tgal
$6,187
-
lb
TOTAL IMPLEMENTED $24,156 $29,158 $10,645
325,577
kWh
$3,624
-
kW-mo/yr
- - $3,700
-
Tgal
$6,187
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Usage Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs