Assessment Year | 2006 |
---|---|
Principal Product | Rocket Motor |
NAICS | 336415: Guided Missile and Space Vehicle Propulsion Unit and Propulsion Unit Parts Manufacturing |
SIC | 3764: Guided Missile and Space Vehicle Propulsion Units and Propulsion Unit Parts |
Sales Range | $100 M to 500M |
# of Employees | 900 |
Plant Area |
80,000
ft2
|
Annual Production | 60
pieces
|
Production Hrs. Annual | 8,700
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,677,000 | 42,879,000 |
kWh
|
$0.039 |
Natural Gas | $4,962,900 | 589,770 |
MMBtu
|
$8.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $398,590 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | - | - | - | - |
$100,000
-
MMBtu
|
$(-100,000.0) | |
02 | 2.2113: Repair or replace steam traps | $121,540 | $8,720 | - | - |
$121,540
-
MMBtu
|
- | |
03 | 2.2153: Close off unneeded steam lines | $140,530 | $250,000 | - | - |
$140,530
-
MMBtu
|
- | |
04 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $69,680 | $200,000 | - | - |
$69,680
-
MMBtu
|
- | |
05 | 2.6213: Turn off steam / hot water lines leading to space heating units | $65,810 | $442,960 | - | - |
$65,810
-
MMBtu
|
- | |
06 | 2.7124: Make a practice of turning off lights when not needed | $1,030 | - |
$680
32,520
kWh
|
$350
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $398,590 | $901,680 |
$680
32,520
kWh
|
$350
-
kW-mo/yr
|
$497,560
-
MMBtu
|
$(-100,000.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs