ITAC Assessment: UU0112
ITAC logo
ITAC Assessment: UU0112
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Rocket Motor
NAICS 336415: Guided Missile and Space Vehicle Propulsion Unit and Propulsion Unit Parts Manufacturing
SIC 3764: Guided Missile and Space Vehicle Propulsion Units and Propulsion Unit Parts
Sales Range $100
M
to 500
M
# of Employees 900
Plant Area 80,000
ft2
Annual Production 60
pieces
Production Hrs. Annual 8,700
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,677,000 42,879,000
kWh
Natural Gas $4,962,900 589,770
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $398,590 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.6218: Turn off equipment when not in use - - - - $100,000
-
MMBtu
$(-100,000.0)
02 2.2113: Repair or replace steam traps $121,540 $8,720 - - $121,540
-
MMBtu
-
03 2.2153: Close off unneeded steam lines $140,530 $250,000 - - $140,530
-
MMBtu
-
04 2.1223: Install smaller boiler (increase high fire duty cycle) $69,680 $200,000 - - $69,680
-
MMBtu
-
05 2.6213: Turn off steam / hot water lines leading to space heating units $65,810 $442,960 - - $65,810
-
MMBtu
-
06 2.7124: Make a practice of turning off lights when not needed $1,030 - $680
32,520
kWh
$350
-
kW-mo/yr
- -
TOTAL RECOMMENDED $398,590 $901,680 $680
32,520
kWh
$350
-
kW-mo/yr
$497,560
-
MMBtu
$(-100,000.0)
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs