| Assessment Year | 2006 |
|---|---|
| Principal Product | Food Processing Equipment |
| NAICS | 333241: Food Product Machinery Manufacturing |
| SIC | 3556: Food Products Machinery |
| Sales Range | $5 M to 10M |
| # of Employees | 56 |
| Plant Area |
66,000
ft2
|
| Annual Production | 50
pieces
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $8,427 | 327,360 |
kWh
|
$0.026 |
| Electricity Demand | $17,269 | 1,594 |
kW-mo/yr
|
$10.83 |
| Natural Gas | $34,051 | 3,604 |
MMBtu
|
$9.45 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $8,310 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $520 | $435 |
$520
18,330
kWh
|
- | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $950 | $18 |
$360
12,970
kWh
|
$590
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,590 | $2,085 |
$850
30,380
kWh
|
$1,740
-
kW-mo/yr
|
- | |
| 04 | 2.1224: Replace boiler | $1,090 | $800 |
$(-20.0)
(-850)
kWh
|
$(-220.0)
-
kW-mo/yr
|
$1,330
-
MMBtu
|
|
| 05 | 2.7492: Use proper thickness of insulation on building envelope | $1,470 | $8,820 |
$440
15,590
kWh
|
- |
$1,030
-
MMBtu
|
|
| 06 | 2.3212: Optimize plant power factor | $1,690 | $1,860 | - |
$1,690
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $8,310 | $14,018 |
$2,150
76,420
kWh
|
$3,800
-
kW-mo/yr
|
$2,360
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs