Assessment Year | 2006 |
---|---|
Principal Product | Garage Doors |
NAICS | 332321: Metal Window and Door Manufacturing |
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $10 M to 50M |
# of Employees | 210 |
Plant Area |
200,000
ft2
|
Annual Production | 55,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $36,586 | 1,421,380 |
kWh
|
$0.026 |
Electricity Demand | $51,497 | 5,029 |
kW-mo/yr
|
$10.24 |
Natural Gas | $22,259 | 3,162 |
MMBtu
|
$7.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,290 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $21,720 | $10,000 | - |
$21,720
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,510 | $830 |
$1,040
37,000
kWh
|
$1,470
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,490 | $165 |
$620
21,990
kWh
|
$870
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $290 | $740 |
$130
4,770
kWh
|
$160
-
kW-mo/yr
|
- | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $15,000 | $10,000 | - | - |
$15,000
-
lb
|
|
06 | 2.3212: Optimize plant power factor | $4,280 | $4,140 | - |
$4,280
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $45,290 | $25,875 |
$1,790
63,760
kWh
|
$28,500
-
kW-mo/yr
|
$15,000
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs