ITAC Assessment: UU0100
ITAC logo
ITAC Assessment: UU0100
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Garage Doors
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 210
Plant Area 200,000
ft2
Annual Production 55,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $36,586 1,421,380
kWh
Electricity Demand $51,497 5,029
kW-mo/yr
Natural Gas $22,259 3,162
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,290 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.3191: Use demand controller or load shedder $21,720 $10,000 - $21,720
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,510 $830 $1,040
37,000
kWh
$1,470
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,490 $165 $620
21,990
kWh
$870
-
kW-mo/yr
-
04 2.4221: Install compressor air intakes in coolest locations $290 $740 $130
4,770
kWh
$160
-
kW-mo/yr
-
05 3.5315: Lease / purchase baler; sell cardboard to recycler $15,000 $10,000 - - $15,000
-
lb
06 2.3212: Optimize plant power factor $4,280 $4,140 - $4,280
-
kW-mo/yr
-
TOTAL RECOMMENDED $45,290 $25,875 $1,790
63,760
kWh
$28,500
-
kW-mo/yr
$15,000
-
lb
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs