ITAC Assessment: UU0098
ITAC logo
ITAC Assessment: UU0098
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Bottled Water
NAICS 312112: Bottled Water Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 145,000
ft2
Annual Production 3,300,000
pieces
Production Hrs. Annual 5,200
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $39,378 1,367,722
kWh
Electricity Demand $32,894 3,740
kW-mo/yr
Natural Gas $32,027 5,621
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,900 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,900

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.3191: Use demand controller or load shedder $2,060 - - $2,060
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,360 $2,100 $1,050
37,410
kWh
$1,310
-
kW-mo/yr
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,690 $1,000 $370
13,270
kWh
$3,320
-
kW-mo/yr
04 2.4133: Use most efficient type of electric motors $410 $2,880 $160
5,850
kWh
$250
-
kW-mo/yr
05 2.3212: Optimize plant power factor $2,380 $2,040 - $2,380
-
kW-mo/yr
TOTAL RECOMMENDED $10,900 $8,020 $1,580
56,530
kWh
$9,320
-
kW-mo/yr
TOTAL IMPLEMENTED $10,900 $8,020 $1,580
56,530
kWh
$9,320
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs