Assessment Year | 2004 |
---|---|
Principal Product | electric signs |
NAICS | 339950: Sign Manufacturing |
SIC | 3993: Signs and Advertising Specialties |
Sales Range | $1 M to 5M |
# of Employees | 78 |
Plant Area |
54,229
ft2
|
Annual Production | 150
pieces
|
Production Hrs. Annual | 2,560
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $31,255 | 722,200 |
kWh
|
$0.043 |
Electricity Demand | $25,891 | 3,046 |
kW-mo/yr
|
$8.50 |
Natural Gas | $26,053 | 4,644 |
MMBtu
|
$5.61 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,084 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7243: Improve air circulation with destratification fans / other methods | $8,250 | $8,000 |
$(-460.0)
(-10,000)
kWh
|
$(-10.0)
-
kW-mo/yr
|
$8,720
-
MMBtu
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,080 | $860 |
$610
13,390
kWh
|
$470
-
kW-mo/yr
|
- | - | - | - | |
03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $990 | $6,000 | - | - | - |
$990
-
lb
|
- | - | |
04 | 3.5217: Reuse / recycle/ sell paper products | $2,434 | - | - | - | - |
$2,434
-
lb
|
- | - | |
05 | 2.3191: Use demand controller or load shedder | $2,700 | $2,500 | - |
$2,700
-
kW-mo/yr
|
- | - | - | - | |
06 | 4.111: Add equipment/ operators to reduce production bottleneck | $10,500 | $15,000 | - | - | - | - | - | $10,500 | |
07 | 4.811: Demolish old building to reduce tax and insurance bills | $130 | - | - | - | - | - | $130 | - | |
TOTAL RECOMMENDED | $26,084 | $32,360 |
$150
3,390
kWh
|
$3,160
-
kW-mo/yr
|
$8,720
-
MMBtu
|
$3,424
-
lb
|
$130 | $10,500 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs