ITAC Assessment: UU0073
ITAC logo
ITAC Assessment: UU0073
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product electric signs
NAICS 339950: Sign Manufacturing
SIC 3993: Signs and Advertising Specialties
Sales Range $1
M
to 5
M
# of Employees 78
Plant Area 54,229
ft2
Annual Production 150
pieces
Production Hrs. Annual 2,560
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,255 722,200
kWh
Electricity Demand $25,891 3,046
kW-mo/yr
Natural Gas $26,053 4,644
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,084 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Increase in Production Savings
01 2.7243: Improve air circulation with destratification fans / other methods $8,250 $8,000 $(-460.0)
(-10,000)
kWh
$(-10.0)
-
kW-mo/yr
$8,720
-
MMBtu
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,080 $860 $610
13,390
kWh
$470
-
kW-mo/yr
- - - -
03 3.6193: Install equipment (eg compactor) to reduce disposal costs $990 $6,000 - - - $990
-
lb
- -
04 3.5217: Reuse / recycle/ sell paper products $2,434 - - - - $2,434
-
lb
- -
05 2.3191: Use demand controller or load shedder $2,700 $2,500 - $2,700
-
kW-mo/yr
- - - -
06 4.111: Add equipment/ operators to reduce production bottleneck $10,500 $15,000 - - - - - $10,500
07 4.811: Demolish old building to reduce tax and insurance bills $130 - - - - - $130 -
TOTAL RECOMMENDED $26,084 $32,360 $150
3,390
kWh
$3,160
-
kW-mo/yr
$8,720
-
MMBtu
$3,424
-
lb
$130 $10,500
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs