ITAC Assessment: UA0252
ITAC logo
ITAC Assessment: UA0252
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Tractor Attachments
NAICS 333111: Farm Machinery and Equipment Manufacturing
SIC 3523: Farm Machinery and Equipment
Sales Range $50
M
to 100
M
# of Employees 490
Plant Area 530,000
ft2
Annual Production 20,000
units
Production Hrs. Annual 7,344
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $431,904 7,415,590
kWh
Electricity Demand $74,475 18,121
kW-mo/yr
Electricity Fees $15,645 -
Natural Gas $578,789 62,085
MMBtu
LPG $25,143 1,734
MMBtu
TOTAL YEARLY COSTS $1,125,956
RECOMMENDED SAVINGS* $50,218 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $50,218

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7135: Install occupancy sensors $32,927 $257 $31,940
548,421
kWh
- $987 -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,634 $850 $3,180
54,604
kWh
$345
-
kW-mo/yr
$109 -
03 2.2437: Recover waste heat from equipment $13,657 $8,080 - - - $13,657
-
MMBtu
TOTAL RECOMMENDED $50,218 $9,187 $35,120
603,025
kWh
$345
-
kW-mo/yr
$1,096 $13,657
-
MMBtu
TOTAL IMPLEMENTED $50,218 $9,187 $35,120
603,025
kWh
$345
-
kW-mo/yr
$1,096 $13,657
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs