Assessment Year | 2004 |
---|---|
Principal Product | climbing equipment |
NAICS | 339920: Sporting and Athletic Goods Manufacturing |
SIC | 3949: Sporting and Athletic Goods, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
96,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 4,290
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $50,345 | 1,815,080 |
kWh
|
$0.028 |
Electricity Demand | $53,258 | 6,575 |
kW-mo/yr
|
$8.10 |
Electricity Fees | $9,566 | - |
|
- |
Natural Gas | $6,625 | 1,275 |
MMBtu
|
$5.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,693 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,983 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $4,060 | $5,520 | - | - | $4,060 | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,450 | - | - |
$6,450
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,345 | $1,100 |
$690
24,000
kWh
|
$655
-
kW-mo/yr
|
- | |
04 | 2.7144: Install spectral reflectors / delamp | $1,188 | $225 |
$602
21,000
kWh
|
$586
-
kW-mo/yr
|
- | |
05 | 2.2136: Install / repair insulation on steam lines | $1,650 | $675 |
$1,650
57,600
kWh
|
- | - | |
TOTAL RECOMMENDED | $14,693 | $7,520 |
$2,942
102,600
kWh
|
$7,691
-
kW-mo/yr
|
$4,060 | ||
TOTAL IMPLEMENTED | $8,983 | $1,325 |
$1,292
45,000
kWh
|
$7,691
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs