| Assessment Year | 2004 |
|---|---|
| Principal Product | minerals |
| NAICS | 325412: Pharmaceutical Preparation Manufacturing |
| SIC | 2834: Pharmaceutical Preparations |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
200,000
ft2
|
| Annual Production | 4,700,000
lb
|
| Production Hrs. Annual | 4,212
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $45,407 | 1,637,040 |
kWh
|
$0.028 |
| Electricity Demand | $47,507 | 5,865 |
kW-mo/yr
|
$8.10 |
| Electricity Fees | $13,947 | - |
|
- |
| Natural Gas | $111,955 | 20,683 |
MMBtu
|
$5.41 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,245 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,393 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $14,228 | $70,000 |
$(-821.0)
(-25,311)
kWh
|
$(-757.0)
-
kW-mo/yr
|
$15,806
-
MMBtu
|
- | |
| 02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $2,876 | $2,255 |
$(-2,281.0)
(-73,440)
kWh
|
$(-1,022.0)
-
kW-mo/yr
|
$6,179
-
MMBtu
|
- | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $2,624 | $2,400 |
$125
3,851
kWh
|
$2,499
-
kW-mo/yr
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $1,252 | $1,754 | - | - |
$1,252
-
MMBtu
|
- | |
| 05 | 2.6218: Turn off equipment when not in use | $1,785 | - |
$869
26,835
kWh
|
$916
-
kW-mo/yr
|
- | - | |
| 06 | 2.8114: Change rate schedules or other changes in utility service | $5,480 | - | - | - | - | $5,480 | |
| TOTAL RECOMMENDED | $28,245 | $76,409 |
$(-2,108.0)
(-68,065)
kWh
|
$1,636
-
kW-mo/yr
|
$23,237
-
MMBtu
|
$5,480 | ||
| TOTAL IMPLEMENTED | $11,393 | $4,009 |
$(-1,412.0)
(-46,605)
kWh
|
$(-106.0)
-
kW-mo/yr
|
$7,431
-
MMBtu
|
$5,480 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs