Assessment Year | 2004 |
---|---|
Principal Product | airbag inflators |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 750 |
Plant Area |
586,000
ft2
|
Annual Production | 12,000,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,017,508 | 32,929,066 |
kWh
|
$0.031 |
Electricity Demand | $349,694 | 59,543 |
kW-mo/yr
|
$5.87 |
Electricity Fees | $21,108 | - |
|
- |
Natural Gas | $45,856 | 9,664 |
MMBtu
|
$4.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $137,099 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $50,143 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $12,130 | $9,651 |
$9,299
297,500
kWh
|
$2,831
-
kW-mo/yr
|
- | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $20,658 | $20,658 |
$15,838
505,000
kWh
|
$4,820
-
kW-mo/yr
|
- | - | |
03 | 2.4131: Size electric motors for peak operating efficiency | $23,500 | $15,630 |
$17,739
565,600
kWh
|
$5,761
-
kW-mo/yr
|
- | - | |
04 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $6,386 | $275 | - | - |
$4,656
-
MMBtu
|
$1,730
-
Tgal
|
|
05 | 2.7144: Install spectral reflectors / delamp | $29,485 | $6,260 |
$22,633
721,600
kWh
|
$6,852
-
kW-mo/yr
|
- | - | |
06 | 2.7145: Install skylights | $32,748 | $272,000 |
$32,618
1,040,000
kWh
|
- |
$130
-
MMBtu
|
- | |
07 | 2.2521: Isolate steam lines to avoid heating air conditioned areas | $12,192 | $8,860 |
$10,050
320,500
kWh
|
$2,142
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $137,099 | $333,334 |
$108,177
3,450,200
kWh
|
$22,406
-
kW-mo/yr
|
$4,786
-
MMBtu
|
$1,730
-
Tgal
|
||
TOTAL IMPLEMENTED | $50,143 | $26,918 |
$38,471
1,226,600
kWh
|
$11,672
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs