ITAC Assessment: UU0016
ITAC logo
ITAC Assessment: UU0016
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Paper Products
NAICS
n/a
SIC 2678: Stationery, Tablets, and Related Products
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 22,500
ft2
Annual Production 9,000,000
lb
Production Hrs. Annual 4,590
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $99,083 4,115,280
kWh
Electricity Demand $62,825 9,036
kW-mo/yr
Electricity Fees $14,574 -
Natural Gas $23,653 3,028
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $61,116 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,383

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7145: Install skylights $53,853 $16,000 $22,951
759,200
kWh
$30,902
-
kW-mo/yr
02 2.4221: Install compressor air intakes in coolest locations $3,195 $915 $2,046
67,686
kWh
$1,149
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $188 $35 $120
3,994
kWh
$68
-
kW-mo/yr
04 2.4314: Use synthetic lubricant $330 $400 $210
6,961
kWh
$120
-
kW-mo/yr
05 2.4133: Use most efficient type of electric motors $3,550 $6,283 $2,497
82,658
kWh
$1,053
-
kW-mo/yr
TOTAL RECOMMENDED $61,116 $23,633 $27,824
920,499
kWh
$33,292
-
kW-mo/yr
TOTAL IMPLEMENTED $3,383 $950 $2,166
71,680
kWh
$1,217
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs