ITAC Assessment: UU0013
ITAC logo
ITAC Assessment: UU0013
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Paper products
NAICS
n/a
SIC 2750:
Sales Range $500
k
to 1
M
# of Employees 10
Plant Area 15,000
ft2
Annual Production 100
lb
Production Hrs. Annual 4,590
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,429 54,360
kWh
Electricity Demand $2,508 324
kW-mo/yr
Electricity Fees $517 -
Natural Gas $1,073 144
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,274 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $774

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $457 $2,636 $392
12,958
kWh
$65
-
kW-mo/yr
-
02 2.3212: Optimize plant power factor $317 $500 - $317
-
kW-mo/yr
-
03 4.451: Add additional production shift $2,500 - - - $2,500
TOTAL RECOMMENDED $3,274 $3,136 $392
12,958
kWh
$382
-
kW-mo/yr
$2,500
TOTAL IMPLEMENTED $774 $3,136 $392
12,958
kWh
$382
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs