Assessment Year | 2001 |
---|---|
Principal Product | Gilsonite |
NAICS |
n/a
|
SIC | 2893: Printing Ink |
Sales Range | $5 M to 10M |
# of Employees | 45 |
Plant Area |
15,000
ft2
|
Annual Production | 25,000
ton
|
Production Hrs. Annual | 4,590
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $409,092 | 13,028,400 |
kWh
|
$0.031 |
Electricity Demand | $382,936 | 34,812 |
kW-mo/yr
|
$11.00 |
Electricity Fees | $26,376 | - |
|
- |
Natural Gas | $676,288 | 138,069 |
MMBtu
|
$4.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $48,036 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,600 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $23,054 | $55,276 |
$15,524
494,416
kWh
|
$7,530
-
kW-mo/yr
|
- | |
02 | 2.4314: Use synthetic lubricant | $8,209 | $250 |
$3,959
126,100
kWh
|
$4,250
-
kW-mo/yr
|
- | |
03 | 2.2437: Recover waste heat from equipment | $8,154 | $7,500 | - | - |
$8,154
-
MMBtu
|
|
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,600 | $5,000 | - |
$6,600
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,019 | $1,000 |
$1,231
39,210
kWh
|
$788
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $48,036 | $69,026 |
$20,714
659,726
kWh
|
$19,168
-
kW-mo/yr
|
$8,154
-
MMBtu
|
||
TOTAL IMPLEMENTED | $6,600 | $5,000 | - |
$6,600
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs