Assessment Year | 2001 |
---|---|
Principal Product | phosphate slurry |
NAICS |
n/a
|
SIC | 2875: Fertilizers, Mixing Only |
Sales Range | $1 M to 5M |
# of Employees | 100 |
Plant Area |
15,000
ft2
|
Annual Production | 2,500,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,706,262 | 84,620,000 |
kWh
|
$0.020 |
Electricity Demand | $822,034 | 143,700 |
kW-mo/yr
|
$5.72 |
Electricity Fees | $60,313 | - |
|
- |
Natural Gas | $109,427 | 21,612 |
MMBtu
|
$5.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $126,110 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $125,146 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $55,587 | $47,184 |
$43,056
1,971,679
kWh
|
$12,531
-
kW-mo/yr
|
|
02 | 2.4314: Use synthetic lubricant | $44,401 | $4,000 |
$34,386
1,577,340
kWh
|
$10,015
-
kW-mo/yr
|
|
03 | 2.4133: Use most efficient type of electric motors | $24,413 | $85,168 |
$18,899
865,519
kWh
|
$5,514
-
kW-mo/yr
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $964 | $3,417 |
$695
31,798
kWh
|
$269
-
kW-mo/yr
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $745 | $140 |
$537
24,594
kWh
|
$208
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $126,110 | $139,909 |
$97,573
4,470,930
kWh
|
$28,537
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $125,146 | $136,492 |
$96,878
4,439,132
kWh
|
$28,268
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs