Assessment Year | 2001 |
---|---|
Principal Product | Plastic coating of rebar |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $1 M to 5M |
# of Employees | 50 |
Plant Area |
35,500
ft2
|
Annual Production | 1,000
ton
|
Production Hrs. Annual | 4,590
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $74,215 | 2,822,800 |
kWh
|
$0.026 |
Electricity Demand | $48,497 | 6,324 |
kW-mo/yr
|
$7.67 |
Electricity Fees | $7,617 | - |
|
- |
Natural Gas | $16,099 | 2,807 |
MMBtu
|
$5.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,488 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,252 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,523 | $125 |
$2,401
79,448
kWh
|
$1,122
-
kW-mo/yr
|
- | |
02 | 2.4314: Use synthetic lubricant | $423 | $400 |
$305
10,105
kWh
|
$118
-
kW-mo/yr
|
- | |
03 | 2.2437: Recover waste heat from equipment | $1,204 | $460 | - | - |
$1,204
-
MMBtu
|
|
04 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $5,102 | $2,600 |
$3,478
115,072
kWh
|
$1,624
-
kW-mo/yr
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,236 | $1,844 |
$915
30,291
kWh
|
$321
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $11,488 | $5,429 |
$7,099
234,916
kWh
|
$3,185
-
kW-mo/yr
|
$1,204
-
MMBtu
|
||
TOTAL IMPLEMENTED | $10,252 | $3,585 |
$6,184
204,625
kWh
|
$2,864
-
kW-mo/yr
|
$1,204
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs