ITAC Assessment: UU0004
ITAC logo
ITAC Assessment: UU0004
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Commercial furniture
NAICS
n/a
SIC 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area 185,000
ft2
Annual Production 10,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,186 960,800
kWh
Electricity Demand $37,401 4,530
kW-mo/yr
Electricity Fees $3,888 -
Natural Gas $54,663 9,559
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $78,928 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,397

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,903 $875 $863
28,556
kWh
$1,040
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,988 $6,235 - $2,988
-
kW-mo/yr
- - -
03 2.4133: Use most efficient type of electric motors $11,095 $21,780 $7,055
233,480
kWh
$4,040
-
kW-mo/yr
- - -
04 2.2437: Recover waste heat from equipment $4,328 $2,000 - - $4,328
-
gal
- -
05 3.8132: Use less toxic and volatile solvent substitutes $1,494 - - - - $1,494
-
gal
-
06 4.711: Initiate a total quality management program $57,120 $1,200 - - - - $57,120
TOTAL RECOMMENDED $78,928 $32,090 $7,918
262,036
kWh
$8,068
-
kW-mo/yr
$4,328
-
gal
$1,494
-
gal
$57,120
TOTAL IMPLEMENTED $3,397 $875 $863
28,556
kWh
$1,040
-
kW-mo/yr
- $1,494
-
gal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs