Assessment Year | 2001 |
---|---|
Principal Product | Commercial furniture |
NAICS |
n/a
|
SIC | 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers |
Sales Range | $5 M to 10M |
# of Employees | 70 |
Plant Area |
185,000
ft2
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $25,186 | 960,800 |
kWh
|
$0.026 |
Electricity Demand | $37,401 | 4,530 |
kW-mo/yr
|
$8.26 |
Electricity Fees | $3,888 | - |
|
- |
Natural Gas | $54,663 | 9,559 |
MMBtu
|
$5.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $78,928 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,397 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,903 | $875 |
$863
28,556
kWh
|
$1,040
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,988 | $6,235 | - |
$2,988
-
kW-mo/yr
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $11,095 | $21,780 |
$7,055
233,480
kWh
|
$4,040
-
kW-mo/yr
|
- | - | - | |
04 | 2.2437: Recover waste heat from equipment | $4,328 | $2,000 | - | - |
$4,328
-
gal
|
- | - | |
05 | 3.8132: Use less toxic and volatile solvent substitutes | $1,494 | - | - | - | - |
$1,494
-
gal
|
- | |
06 | 4.711: Initiate a total quality management program | $57,120 | $1,200 | - | - | - | - | $57,120 | |
TOTAL RECOMMENDED | $78,928 | $32,090 |
$7,918
262,036
kWh
|
$8,068
-
kW-mo/yr
|
$4,328
-
gal
|
$1,494
-
gal
|
$57,120 | ||
TOTAL IMPLEMENTED | $3,397 | $875 |
$863
28,556
kWh
|
$1,040
-
kW-mo/yr
|
- |
$1,494
-
gal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs