Assessment Year | 2017 |
---|---|
Principal Product | Wood office furniture |
NAICS | 337214: Office Furniture (except Wood) Manufacturing |
SIC | 2521: Wood Office Furniture |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
110,000
ft2
|
Annual Production | 75,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $167,168 | 2,414,140 |
kWh
|
$0.069 |
Electricity Demand | $99,123 | 5,167 |
kW-mo/yr
|
$19.18 |
Natural Gas | $44,884 | 5,864 |
MMBtu
|
$7.65 |
TOTAL YEARLY COSTS | $311,175 | |||
RECOMMENDED SAVINGS* | $24,290 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,932 | $3,000 |
$1,081
15,665
kWh
|
$1,851
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $896 | $2,400 |
$896
12,993
kWh
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $20,120 | $18,000 |
$20,120
291,599
kWh
|
- | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $342 | $1,500 | - | - |
$342
-
MMBtu
|
|
TOTAL RECOMMENDED | $24,290 | $24,900 |
$22,097
320,257
kWh
|
$1,851
-
kW-mo/yr
|
$342
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs