ITAC Assessment: SD0062
ITAC logo
ITAC Assessment: SD0062
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product WHOLESALE BEEF
NAICS
n/a
SIC 2011: Meat Packing Plants
Sales Range $1
M
to 5
M
# of Employees 80
Plant Area
n/a
Annual Production 33,200
pieces
Production Hrs. Annual 6,000
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $143,436 1,892,732
kWh
Natural Gas $34,643 6,025
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,510 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,891

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $1,044 $950 $1,044
13,775
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,350 - $2,350
31,067
kWh
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $127 $80 $127
1,758
kWh
- -
04 2.2425: Use flue gases to heat process or service water $11,880 $18,000 - $11,880
-
MMBtu
-
05 2.2136: Install / repair insulation on steam lines $242 $200 - $242
-
MMBtu
-
06 2.1131: Repair faulty insulation in furnaces, boilers, etc $370 $47 - $370
-
MMBtu
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,122 - $1,231
16,120
kWh
- $(-109.0)
08 2.7142: Utilize higher efficiency lamps and/or ballasts $375 - $368
4,103
kWh
- $7
TOTAL RECOMMENDED $17,510 $19,277 $5,120
66,823
kWh
$12,492
-
MMBtu
$(-102.0)
TOTAL IMPLEMENTED $3,891 $1,077 $3,521
46,600
kWh
$370
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs