ITAC Assessment: UM0457
ITAC logo
ITAC Assessment: UM0457
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product brake drums and rotors
NAICS 331511: Iron Foundries
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $100
M
to 500
M
# of Employees 399
Plant Area 370,000
ft2
Annual Production 176,000,000
lb
Production Hrs. Annual 8,000
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $4,772,198 90,434,247
kWh
Electricity Demand $1,762,347 207,826
kW-mo/yr
Natural Gas $719,727 75,769
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $579,336 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $162,816

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $261,975 $300,000 $555,989
10,490,372
kWh
- $(-294,014.0)
-
MMBtu
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $162,816 $1,000 - $162,816
-
kW-mo/yr
-
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $154,545 $50,000 $172,548
3,255,632
kWh
$73,267
-
kW-mo/yr
$(-91,270.0)
-
MMBtu
TOTAL RECOMMENDED $579,336 $351,000 $728,537
13,746,004
kWh
$236,083
-
kW-mo/yr
$(-385,284.0)
-
MMBtu
TOTAL IMPLEMENTED $162,816 $1,000 - $162,816
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs