ITAC Assessment: UM0416
ITAC logo
ITAC Assessment: UM0416
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Bituminous Hot Mix Asphalt
NAICS 324121: Asphalt Paving Mixture and Block Manufacturing
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $5
M
to 10
M
# of Employees 10
Plant Area 100,000
ft2
Annual Production 100,000
units
Production Hrs. Annual 1,705
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $50,503 524,000
kWh
Natural Gas $286,468 54,774
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $847 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $222

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $625 $200 $625
6,480
kWh
02 2.7135: Install occupancy sensors $222 $450 $222
2,302
kWh
TOTAL RECOMMENDED $847 $650 $847
8,782
kWh
TOTAL IMPLEMENTED $222 $450 $222
2,302
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs