ITAC Assessment: UM0403
ITAC logo
ITAC Assessment: UM0403
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product plastic products, sheet steel, PVC
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 72
Plant Area 51,781
ft2
Annual Production 2,415,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,642 1,648,759
kWh
Electricity Demand $56,284 4,117
kW-mo/yr
Electricity Fees $43,276 -
Natural Gas $31,535 3,581
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,187 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,740

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,740 $6,369 $4,006
130,784
kWh
$2,734
-
kW-mo/yr
02 2.1131: Repair faulty insulation in furnaces, boilers, etc $5,872 $1,175 $3,493
89,232
kWh
$2,379
-
kW-mo/yr
03 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $5,116 $16,500 $5,116
132,537
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $921 $1,000 $921
23,864
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $538 $200 $538
13,946
kWh
-
TOTAL RECOMMENDED $19,187 $25,244 $14,074
390,363
kWh
$5,113
-
kW-mo/yr
TOTAL IMPLEMENTED $6,740 $6,369 $4,006
130,784
kWh
$2,734
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs