Assessment Year | 2004 |
---|---|
Principal Product | Automotive Control Arms |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 290 |
Plant Area |
135,000
ft2
|
Annual Production | 1,400,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $117,199 | 10,050,518 |
kWh
|
$0.012 |
Electricity Demand | $351,291 | 21,931 |
kW-mo/yr
|
$16.02 |
Electricity Fees | $1,431 | - |
|
- |
Natural Gas | $399,144 | 60,547 |
MMBtu
|
$6.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $75,006 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,304 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads | $46,210 | $29,000 |
$80
6,714
kWh
|
- |
$66,700
-
MMBtu
|
$(-20,570.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,116 | $18,242 |
$4,810
412,523
kWh
|
$8,306
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,108 | $11,108 |
$2,964
254,179
kWh
|
$8,144
-
kW-mo/yr
|
- | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $4,376 | $1,200 | - | - |
$4,376
-
MMBtu
|
- | |
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $196 | $400 |
$196
16,805
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $75,006 | $59,950 |
$8,050
690,221
kWh
|
$16,450
-
kW-mo/yr
|
$71,076
-
MMBtu
|
$(-20,570.0) | ||
TOTAL IMPLEMENTED | $11,304 | $11,508 |
$3,160
270,984
kWh
|
$8,144
-
kW-mo/yr
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs