ITAC Assessment: UM0266
ITAC logo
ITAC Assessment: UM0266
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Welded Steel Pressure Vessels
NAICS 332439: Other Metal Container Manufacturing
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $5
M
to 10
M
# of Employees 69
Plant Area 160,932
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,589 1,346,360
kWh
Electricity Demand $29,934 7,014
kW-mo/yr
Electricity Fees $5,618 -
Natural Gas $87,892 12,632
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,214 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,125

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.2425: Use flue gases to heat process or service water $11,825 $4,500 - - $11,825
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,131 $7,512 $4,781
101,234
kWh
$1,350
-
kW-mo/yr
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,042 $900 $3,971
84,294
kWh
$1,071
-
kW-mo/yr
- -
04 2.2443: Re-use or recycle hot or cold process exhaust air $2,182 $1,000 - - $2,182
-
MMBtu
-
05 2.4239: Eliminate or reduce compressed air usage $1,847 $2,000 $1,450
30,851
kWh
$397
-
kW-mo/yr
- -
06 3.1191: Change procedures / equipment / operating conditions $1,400 $700 - - - $1,400
-
lb
07 2.7243: Improve air circulation with destratification fans / other methods $1,312 $3,500 - - $1,312
-
MMBtu
-
08 2.7244: Revise smoke cleanup from operations $1,614 $500 - - $1,614
-
MMBtu
-
09 2.7135: Install occupancy sensors $1,195 $603 $1,195
25,428
kWh
- - -
10 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses $666 $610 - - $666
-
MMBtu
-
TOTAL RECOMMENDED $33,214 $21,825 $11,397
241,807
kWh
$2,818
-
kW-mo/yr
$17,599
-
MMBtu
$1,400
-
lb
TOTAL IMPLEMENTED $27,125 $16,022 $10,202
216,379
kWh
$2,818
-
kW-mo/yr
$14,105
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs