| Assessment Year | 2004 |
|---|---|
| Principal Product | Resistance Welding Units |
| NAICS | 333992: Welding and Soldering Equipment Manufacturing |
| SIC | 3548: Electric and Gas Welding and Soldering Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
75,000
ft2
|
| Annual Production | 5,600
pieces
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $49,593 | 1,023,920 |
kWh
|
$0.048 |
| Electricity Demand | $12,745 | 3,723 |
kW-mo/yr
|
$3.42 |
| Electricity Fees | $1,494 | - |
|
- |
| Natural Gas | $22,933 | 2,945 |
MMBtu
|
$7.79 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,848 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,194 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7444: Close holes and openings in building such as broken windows | $3,974 | $1,200 | - | - |
$4,074
-
MMBtu
|
$(-100.0) | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,373 | $300 |
$2,830
58,432
kWh
|
$543
-
kW-mo/yr
|
- | - | |
| 03 | 2.7229: Air condition only space necessary | $2,293 | $1,410 | - | - |
$2,293
-
MMBtu
|
- | |
| 04 | 2.2437: Recover waste heat from equipment | $2,197 | $500 | - | - |
$2,197
-
MMBtu
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,427 | $1,910 |
$1,197
24,720
kWh
|
$230
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,194 | $1,248 |
$1,002
20,685
kWh
|
$192
-
kW-mo/yr
|
- | - | |
| 07 | 2.7135: Install occupancy sensors | $4,751 | $27,856 |
$4,751
98,103
kWh
|
- | - | - | |
| 08 | 2.4239: Eliminate or reduce compressed air usage | $639 | $1,000 |
$536
11,077
kWh
|
$103
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $19,848 | $35,424 |
$10,316
213,017
kWh
|
$1,068
-
kW-mo/yr
|
$8,564
-
MMBtu
|
$(-100.0) | ||
| TOTAL IMPLEMENTED | $1,194 | $1,248 |
$1,002
20,685
kWh
|
$192
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs