| Assessment Year | 2004 |
|---|---|
| Principal Product | Fuel and Brake Systems |
| NAICS | 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 179 |
| Plant Area |
57,000
ft2
|
| Annual Production | 1,750,000
pieces
|
| Production Hrs. Annual | 4,128
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $106,096 | 1,835,600 |
kWh
|
$0.058 |
| Electricity Demand | $89,393 | 7,106 |
kW-mo/yr
|
$12.58 |
| Electricity Fees | $9,241 | - |
|
- |
| Natural Gas | $15,596 | 2,049 |
MMBtu
|
$7.61 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $91,053 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $43,405 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $38,413 | $10,000 | - |
$35,325
-
kW-mo/yr
|
- | $3,088 | - | - | |
| 02 | 3.4111: Use closed cycle process to minimize waste water production | $33,620 | $12,000 |
$(-182.0)
3,096
kWh
|
$(-113.0)
-
kW-mo/yr
|
- | - | $(-12.0) |
$33,927
-
Tgal
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,181 | $13,690 |
$4,246
73,463
kWh
|
$3,935
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.2437: Recover waste heat from equipment | $4,671 | $1,000 | - | - |
$4,671
-
MMBtu
|
- | - | - | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $2,831 | $2,000 |
$1,734
30,000
kWh
|
$1,097
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,283 | $1,050 |
$1,398
24,195
kWh
|
$885
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.7135: Install occupancy sensors | $1,054 | $1,564 |
$1,054
18,231
kWh
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $91,053 | $41,304 |
$8,250
148,985
kWh
|
$41,129
-
kW-mo/yr
|
$4,671
-
MMBtu
|
$3,088 | $(-12.0) |
$33,927
-
Tgal
|
||
| TOTAL IMPLEMENTED | $43,405 | $16,050 |
$2,950
57,291
kWh
|
$1,869
-
kW-mo/yr
|
$4,671
-
MMBtu
|
- | $(-12.0) |
$33,927
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs