ITAC Assessment: UM0235
ITAC logo
ITAC Assessment: UM0235
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Commercial/Residential Hardware, Small Engine Components, Automotive, Ga
NAICS 331523: Nonferrous Metal Die-Casting Foundries
SIC 3364: Nonferrous Die-Castings, Except Aluminum
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 115,000
ft2
Annual Production 15,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $270,668 8,539,200
kWh
Electricity Demand $168,020 17,136
kW-mo/yr
Electricity Fees $32,333 -
Natural Gas $189,545 68,653
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $218,794 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,991

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Primary Product Savings
01 3.1192: Reduce scrap production $109,333 $9,600 - - - $109,333
02 4.111: Add equipment/ operators to reduce production bottleneck $96,000 $300,000 - - $96,000 -
03 2.4239: Eliminate or reduce compressed air usage $7,576 $9,600 $4,680
147,648
kWh
$2,896
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,470 $9,227 $1,843
57,618
kWh
$1,627
-
kW-mo/yr
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,415 $675 $1,492
47,069
kWh
$923
-
kW-mo/yr
- -
TOTAL RECOMMENDED $218,794 $329,102 $8,015
252,335
kWh
$5,446
-
kW-mo/yr
$96,000 $109,333
TOTAL IMPLEMENTED $9,991 $10,275 $6,172
194,717
kWh
$3,819
-
kW-mo/yr
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs