Assessment Year | 2013 |
---|---|
Principal Product | Photochemicals, Radiation Cured Chemicals and Additives |
NAICS | 325199: All Other Basic Organic Chemical Manufacturing |
SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 40 |
Plant Area |
37,000
ft2
|
Annual Production | 130
ton
|
Production Hrs. Annual | 4,335
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $140,800 | 1,292,127 |
kWh
|
$0.11 |
Electricity Demand | $53,203 | 4,498 |
kW-mo/yr
|
$11.83 |
Electricity Fees | $6,066 | - |
|
- |
Natural Gas | $68,752 | 5,030 |
MMBtu
|
$13.67 |
Fuel Oil #2 | $4,743 | 169 |
MMBtu
|
$28.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,697 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,335 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $17,618 | $35,000 |
$17,618
167,473
kWh
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $6,430 | $25,000 |
$7,063
67,141
kWh
|
$2,834
-
kW-mo/yr
|
$(-3,467.0)
-
MMBtu
|
|
03 | 2.2611: Moderate cooling tower outlet temperature | $6,314 | $14,000 |
$6,314
60,021
kWh
|
- | - | |
04 | 2.2136: Install / repair insulation on steam lines | $2,170 | $2,000 | - | - |
$2,170
-
MMBtu
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,165 | $4,055 |
$1,601
15,215
kWh
|
$564
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $34,697 | $80,055 |
$32,596
309,850
kWh
|
$3,398
-
kW-mo/yr
|
$(-1,297.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $4,335 | $6,055 |
$1,601
15,215
kWh
|
$564
-
kW-mo/yr
|
$2,170
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs