Assessment Year | 2002 |
---|---|
Principal Product | Fabricated Assemblies |
NAICS | 332420: Metal Tank (Heavy Gauge) Manufacturing |
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 78 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $189,569 | 3,053,729 |
kWh
|
$0.062 |
Electricity Demand | $79,422 | 9,252 |
kW-mo/yr
|
$8.58 |
Electricity Fees | $9,924 | - |
|
- |
Natural Gas | $227,448 | 34,803 |
MMBtu
|
$6.54 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $69,658 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $65,874 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1114: Limit and control secondary combustion air in furnace | $28,900 | $10,000 | - | - |
$28,900
-
MMBtu
|
|
02 | 2.7243: Improve air circulation with destratification fans / other methods | $23,074 | $1,750 | - | - |
$23,074
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,900 | $1,275 |
$12,390
133,220
kWh
|
$1,510
-
kW-mo/yr
|
- | |
04 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $2,523 | $2,000 |
$2,523
27,130
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,261 | $4,000 |
$895
9,620
kWh
|
$366
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $69,658 | $19,025 |
$15,808
169,970
kWh
|
$1,876
-
kW-mo/yr
|
$51,974
-
MMBtu
|
||
TOTAL IMPLEMENTED | $65,874 | $13,025 |
$12,390
133,220
kWh
|
$1,510
-
kW-mo/yr
|
$51,974
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs