ITAC Assessment: UM0206
ITAC logo
ITAC Assessment: UM0206
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Organic Chemicals
NAICS
n/a
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 210
Plant Area 140,000
ft2
Annual Production 120,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $441,178 19,529,920
kWh
Electricity Demand $532,669 2,562
kW-mo/yr
Electricity Fees $63,151 -
Natural Gas $2,070,352 897,124
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $189,258 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Other Liquid (non-haz) Savings Increase in Production Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $100,000 $5,000 - - - - $100,000
02 3.5313: Increase amount of waste recovered for resale $39,500 $121,500 - - - $39,500
-
gal
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $35,341 $105,000 $20,376
902,000
kWh
$14,965
-
kW-mo/yr
- - -
04 3.4131: Minimize contamination of water before treatment $10,650 $26,000 - - $10,650
-
Tgal
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,767 $525 $1,530
61,457
kWh
$2,237
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $189,258 $258,025 $21,906
963,457
kWh
$17,202
-
kW-mo/yr
$10,650
-
Tgal
$39,500
-
gal
$100,000
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs