ITAC Assessment: UM0203
ITAC logo
ITAC Assessment: UM0203
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Automotive Products
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 355
Plant Area 190,000
ft2
Annual Production 1,500,000
pieces
Production Hrs. Annual 6,468
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $544,581 14,852,628
kWh
Electricity Demand $400,969 33,396
kW-mo/yr
Electricity Fees $12,163 -
Natural Gas $95,864 23,837
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $504,607 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,603 $13,218 $1,557
65,046
kWh
$4,046
-
kW-mo/yr
- -
02 2.7111: Reduce illumination to minimum necessary levels $16,642 $1,150 $9,289
317,612
kWh
$7,353
-
kW-mo/yr
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,091 $600 $1,709
52,447
kWh
$1,382
-
kW-mo/yr
- -
04 2.2437: Recover waste heat from equipment $8,462 $1,000 - - - $8,462
-
MMBtu
05 2.3212: Optimize plant power factor $5,798 $6,400 - - $5,798 -
06 4.631: Install an uninteruptable power supply $465,011 $821,475 - - $465,011 -
TOTAL RECOMMENDED $504,607 $843,843 $12,555
435,105
kWh
$12,781
-
kW-mo/yr
$470,809 $8,462
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs