Assessment Year | 2002 |
---|---|
Principal Product | Automotive Products |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 355 |
Plant Area |
190,000
ft2
|
Annual Production | 1,500,000
pieces
|
Production Hrs. Annual | 6,468
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $544,581 | 14,852,628 |
kWh
|
$0.037 |
Electricity Demand | $400,969 | 33,396 |
kW-mo/yr
|
$12.01 |
Electricity Fees | $12,163 | - |
|
- |
Natural Gas | $95,864 | 23,837 |
MMBtu
|
$4.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $504,607 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,603 | $13,218 |
$1,557
65,046
kWh
|
$4,046
-
kW-mo/yr
|
- | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $16,642 | $1,150 |
$9,289
317,612
kWh
|
$7,353
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,091 | $600 |
$1,709
52,447
kWh
|
$1,382
-
kW-mo/yr
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $8,462 | $1,000 | - | - | - |
$8,462
-
MMBtu
|
|
05 | 2.3212: Optimize plant power factor | $5,798 | $6,400 | - | - | $5,798 | - | |
06 | 4.631: Install an uninteruptable power supply | $465,011 | $821,475 | - | - | $465,011 | - | |
TOTAL RECOMMENDED | $504,607 | $843,843 |
$12,555
435,105
kWh
|
$12,781
-
kW-mo/yr
|
$470,809 |
$8,462
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs