ITAC Assessment: UM0187
ITAC logo
ITAC Assessment: UM0187
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Corrugated Board
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $10
M
to 50
M
# of Employees 104
Plant Area 196,000
ft2
Annual Production 33,600
ton
Production Hrs. Annual 4,160
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $119,630 4,342,907
kWh
Electricity Demand $172,007 9,456
kW-mo/yr
Electricity Fees $7,105 -
Natural Gas $262,576 61,079
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,854 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,460

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.2511: Insulate bare equipment $6,100 $800 - - $6,100
-
MMBtu
-
02 2.2449: Recover heat from exhausted steam, hot air or hot water $4,700 $2,000 - - $1,000
-
MMBtu
$3,700
-
Tgal
03 2.7243: Improve air circulation with destratification fans / other methods $6,344 $5,200 - - $6,344
-
MMBtu
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,181 $375 $312
10,563
kWh
$869
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,279 $1,688 $745
25,160
kWh
$534
-
kW-mo/yr
- -
06 3.4115: Recover and reuse cooling water $10,250 $2,000 - - - $10,250
-
Tgal
TOTAL RECOMMENDED $29,854 $12,063 $1,057
35,723
kWh
$1,403
-
kW-mo/yr
$13,444
-
MMBtu
$13,950
-
Tgal
TOTAL IMPLEMENTED $2,460 $2,063 $1,057
35,723
kWh
$1,403
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs