| Assessment Year | 2001 |
|---|---|
| Principal Product | Heat Treating |
| NAICS |
n/a
|
| SIC | 3398: Metal Heat Treating |
| Sales Range | $5 M to 10M |
| # of Employees | 58 |
| Plant Area |
150,000
ft2
|
| Annual Production | 120,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $96,289 | 3,580,910 |
kWh
|
$0.027 |
| Electricity Demand | $74,673 | 8,460 |
kW-mo/yr
|
$8.83 |
| Electricity Fees | $4,189 | - |
|
- |
| Natural Gas | $672,750 | 178,159 |
MMBtu
|
$3.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $102,390 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 4.611: Begin a practice of predictive / preventative maintenance | $300 | $300 |
$300
11,400
kWh
|
- | - | |
| 02 | 2.2515: Use optimum thickness insulation | $3,470 | $3,540 | - |
$3,470
-
MMBtu
|
- | |
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $94,100 | $71,000 | - |
$94,100
-
MMBtu
|
- | |
| 04 | 4.424: Improve space comfort conditioning | $4,520 | $8,000 | - | - | $4,520 | |
| TOTAL RECOMMENDED | $102,390 | $82,840 |
$300
11,400
kWh
|
$97,570
-
MMBtu
|
$4,520 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs