Assessment Year | 2001 |
---|---|
Principal Product | Steel castings |
NAICS |
n/a
|
SIC | 3325: Steel Foundries, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 287 |
Plant Area |
130,000
ft2
|
Annual Production | 7,500
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $573,074 | 18,050,704 |
kWh
|
$0.032 |
Electricity Demand | $446,501 | 64,764 |
kW-mo/yr
|
$6.89 |
Electricity Fees | $3,360 | - |
|
- |
Natural Gas | $315,435 | 86,686 |
MMBtu
|
$3.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $65,120 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,563 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,563 | $900 |
$739
22,274
kWh
|
$1,824
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $400 | $1,000 |
$400
12,603
kWh
|
- | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $42,749 | $73,500 | n/a | - | - |
$42,749
-
MMBtu
|
04 | 2.1115: Eliminate combustible gas in flue gas | $19,408 | $9,100 | n/a | - | - |
$19,408
-
MMBtu
|
TOTAL RECOMMENDED | $65,120 | $84,500 |
$1,139
34,877
kWh
|
$1,824
-
kW-mo/yr
|
$62,157
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,563 | $900 |
$739
22,274
kWh
|
$1,824
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs