ITAC Assessment: UM0147
ITAC logo
ITAC Assessment: UM0147
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Glass Products
NAICS
n/a
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $10
M
to 50
M
# of Employees 96
Plant Area 84,000
ft2
Annual Production 11,000
ton
Production Hrs. Annual 6,120
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $292,889 5,411,196
kWh
Electricity Demand $53,944 12,816
kW-mo/yr
Electricity Fees $42,807 -
Natural Gas $15,615 2,694
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,223 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,436

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,038 $3,557 $2,717
45,428
kWh
$1,307
-
kW-mo/yr
- - $100 $914 - -
02 2.2628: Utilize a less expensive cooling method $4,796 $2,000 $2,567
69,461
kWh
$2,424
-
kW-mo/yr
- - - - $(-195.0)
-
Tgal
-
03 4.111: Add equipment/ operators to reduce production bottleneck $19,748 $500 $19,748
433,470
kWh
- - - - - - -
04 2.2443: Re-use or recycle hot or cold process exhaust air $7,215 $10,000 - - $7,215
-
MMBtu
- - - - -
05 3.5311: Recover and reuse waste material $1,436 - - - - $1,436
-
lb
- - - -
06 4.611: Begin a practice of predictive / preventative maintenance $990 $400 - - - - - - - $990
TOTAL RECOMMENDED $39,223 $16,457 $25,032
548,359
kWh
$3,731
-
kW-mo/yr
$7,215
-
MMBtu
$1,436
-
lb
$100 $914 $(-195.0)
-
Tgal
$990
TOTAL IMPLEMENTED $1,436 - - - - $1,436
-
lb
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs