| Assessment Year | 1999 |
|---|---|
| Principal Product | Glass Products |
| NAICS |
n/a
|
| SIC | 3231: Glass Products, Made of Purchased Glass |
| Sales Range | $10 M to 50M |
| # of Employees | 96 |
| Plant Area |
84,000
ft2
|
| Annual Production | 11,000
ton
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $292,889 | 5,411,196 |
kWh
|
$0.054 |
| Electricity Demand | $53,944 | 12,816 |
kW-mo/yr
|
$4.21 |
| Electricity Fees | $42,807 | - |
|
- |
| Natural Gas | $15,615 | 2,694 |
MMBtu
|
$5.80 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $39,223 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,436 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,038 | $3,557 |
$2,717
45,428
kWh
|
$1,307
-
kW-mo/yr
|
- | - | $100 | $914 | - | - | |
| 02 | 2.2628: Utilize a less expensive cooling method | $4,796 | $2,000 |
$2,567
69,461
kWh
|
$2,424
-
kW-mo/yr
|
- | - | - | - |
$(-195.0)
-
Tgal
|
- | |
| 03 | 4.111: Add equipment/ operators to reduce production bottleneck | $19,748 | $500 |
$19,748
433,470
kWh
|
- | - | - | - | - | - | - | |
| 04 | 2.2443: Re-use or recycle hot or cold process exhaust air | $7,215 | $10,000 | - | - |
$7,215
-
MMBtu
|
- | - | - | - | - | |
| 05 | 3.5311: Recover and reuse waste material | $1,436 | - | - | - | - |
$1,436
-
lb
|
- | - | - | - | |
| 06 | 4.611: Begin a practice of predictive / preventative maintenance | $990 | $400 | - | - | - | - | - | - | - | $990 | |
| TOTAL RECOMMENDED | $39,223 | $16,457 |
$25,032
548,359
kWh
|
$3,731
-
kW-mo/yr
|
$7,215
-
MMBtu
|
$1,436
-
lb
|
$100 | $914 |
$(-195.0)
-
Tgal
|
$990 | ||
| TOTAL IMPLEMENTED | $1,436 | - | - | - | - |
$1,436
-
lb
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs