Assessment Year | 1999 |
---|---|
Principal Product | Processed Steel Coils |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
370,420
ft2
|
Annual Production | 34,000
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $343,779 | 12,051,583 |
kWh
|
$0.029 |
Electricity Demand | $570,907 | 33,864 |
kW-mo/yr
|
$16.86 |
Electricity Fees | $(-21,002.0) | - |
|
- |
Natural Gas | $639,862 | 151,567 |
MMBtu
|
$4.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $315,502 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $18,168 | $780 |
$8,884
316,237
kWh
|
$9,284
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,110 | $600 |
$877
29,601
kWh
|
$1,233
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7291: Reschedule and rearrange multiple-source heating systems | $27,426 | $13,000 | - | - |
$27,426
-
MMBtu
|
- | - | - | |
04 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $2,688 | $3,600 | - | - |
$2,688
-
MMBtu
|
- | - | - | |
05 | 3.3122: Use filtration, centrifuging to remove contaminants | $225,811 | $90,000 | - | - | - |
$225,811
-
gal
|
- | - | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,613 | - | - | - | - | - |
$2,613
-
lb
|
- | |
07 | 4.454: Modify startup/shutdown times | $36,686 | - | - | - | - | - | - | $36,686 | |
TOTAL RECOMMENDED | $315,502 | $107,980 |
$9,761
345,838
kWh
|
$10,517
-
kW-mo/yr
|
$30,114
-
MMBtu
|
$225,811
-
gal
|
$2,613
-
lb
|
$36,686 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs