| Assessment Year | 1999 |
|---|---|
| Principal Product | Plating Chemicals |
| NAICS |
n/a
|
| SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
257,000
ft2
|
| Annual Production | 17,100,000
lb
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $176,640 | 5,900,645 |
kWh
|
$0.030 |
| Electricity Demand | $216,623 | 20,148 |
kW-mo/yr
|
$10.75 |
| Electricity Fees | $11,674 | - |
|
- |
| Natural Gas | $116,368 | 43,408 |
MMBtu
|
$2.68 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $101,668 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,173 | $10,972 | n/a |
$4,199
142,145
kWh
|
$10,974
-
kW-mo/yr
|
- | - | - |
| 02 | 2.7135: Install occupancy sensors | $616 | $1,400 | n/a |
$616
20,809
kWh
|
- | - | - | - |
| 03 | 2.7221: Lower temperature during the winter season and vice-versa | $2,228 | - | n/a | - | - |
$2,228
-
MMBtu
|
- | - |
| 04 | 2.2136: Install / repair insulation on steam lines | $202 | $510 | n/a | - | - |
$202
-
MMBtu
|
- | - |
| 05 | 2.2113: Repair or replace steam traps | $2,646 | $5,280 | n/a | - | - |
$2,646
-
MMBtu
|
- | - |
| 06 | 2.2121: Increase amount of condensate returned | $14,658 | $6,690 | n/a | - | - |
$6,795
-
MMBtu
|
$7,863
-
Tgal
|
- |
| 07 | 3.4155: Meter waste water | $2,154 | $500 | n/a | - | - | - |
$2,154
-
Tgal
|
- |
| 08 | 4.521: Clear and rent existing space | $63,991 | $63,991 | n/a | - | - | - | - | $63,991 |
| TOTAL RECOMMENDED | $101,668 | $89,343 |
$4,815
162,954
kWh
|
$10,974
-
kW-mo/yr
|
$11,871
-
MMBtu
|
$10,017
-
Tgal
|
$63,991 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs