ITAC Assessment: OK0363
ITAC logo
ITAC Assessment: OK0363
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product FLEXIBLE PVC FILM
NAICS
n/a
SIC 3081: Unsupported Plastics Film and Sheet
Sales Range $5
M
to 10
M
# of Employees 85
Plant Area
n/a
Annual Production 6,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $151,336 2,245,897
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,979 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $7,780 - $7,780
135,991
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,149 - $1,249
28,722
kWh
$(-100.0)
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $774 - $774
13,482
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $845 $276 $845
19,343
kWh
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $201 $167 $243
2,931
kWh
$(-42.0)
06 2.8121: Apply for tax-free status for energy purchases $10,230 - $10,230
-
kWh
-
TOTAL RECOMMENDED $20,979 $443 $21,121
200,469
kWh
$(-142.0)
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs