| Assessment Year | 1999 |
|---|---|
| Principal Product | Metal Building Components |
| NAICS |
n/a
|
| SIC | 3440: |
| Sales Range | $5 M to 10M |
| # of Employees | 22 |
| Plant Area |
48,000
ft2
|
| Annual Production | 4,000,000
units
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $29,115 | 208,089 |
kWh
|
$0.14 |
| Electricity Fees | $(-3,560.0) | - |
|
- |
| Natural Gas | $3,326 | 572 |
MMBtu
|
$5.81 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $84,541 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $1,071 | $1,700 |
$1,071
7,620
kWh
|
- | - | - | - | |
| 02 | 2.7232: Replace existing hvac unit with high efficiency model | $885 | $2,000 | - |
$885
-
MMBtu
|
- | - | - | |
| 03 | 2.7135: Install occupancy sensors | $2,650 | $1,000 |
$2,650
19,050
kWh
|
- | - | - | - | |
| 04 | 3.5217: Reuse / recycle/ sell paper products | $1,800 | - | - | - |
$1,800
-
lb
|
- | - | |
| 05 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $13,800 | - | - | - | - | - | $13,800 | |
| 06 | 4.441: Install automatic packing equipment | $47,700 | $20,000 | - | - | - | $47,700 | - | |
| 07 | 4.513: Re-arrange equipment layout to reduce labor costs | $16,635 | $450 | - | - | - | $16,635 | - | |
| TOTAL RECOMMENDED | $84,541 | $25,150 |
$3,721
26,670
kWh
|
$885
-
MMBtu
|
$1,800
-
lb
|
$64,335 | $13,800 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs