Assessment Year | 1998 |
---|---|
Principal Product | Injection Molded Plastic Automotive Parts |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 480 |
Plant Area |
75,000
ft2
|
Annual Production | 45,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $173,123 | 5,885,698 |
kWh
|
$0.029 |
Electricity Demand | $89,504 | 11,184 |
kW-mo/yr
|
$8.00 |
Electricity Fees | $(-6,449.0) | - |
|
- |
Natural Gas | $7,929 | 1,707 |
MMBtu
|
$4.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $70,163 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,145 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,627 | $3,217 |
$1,027
35,170
kWh
|
$600
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,918 | $17,712 |
$109
4,103
kWh
|
$96
-
kW-mo/yr
|
- | - | - | $4,713 | |
03 | 2.7231: Use radiant heater for spot heating | $1,806 | $192 | - | - |
$1,806
-
MMBtu
|
- | - | - | |
04 | 4.125: | $22,312 | $2,560 | - | - | - |
$22,312
-
lb
|
- | - | |
05 | 3.1191: Change procedures / equipment / operating conditions | $22,600 | $2,400 | - | - | - |
$22,600
-
lb
|
- | - | |
06 | 4.652: Replace existing equipment with more suitable substitutes | $16,900 | $33,000 | - | - | - | - | $16,900 | - | |
TOTAL RECOMMENDED | $70,163 | $59,081 |
$1,136
39,273
kWh
|
$696
-
kW-mo/yr
|
$1,806
-
MMBtu
|
$44,912
-
lb
|
$16,900 | $4,713 | ||
TOTAL IMPLEMENTED | $29,145 | $23,329 |
$1,136
39,273
kWh
|
$696
-
kW-mo/yr
|
- |
$22,600
-
lb
|
- | $4,713 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs