Assessment Year | 1998 |
---|---|
Principal Product | Machined Parts |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 58 |
Plant Area |
49,376
ft2
|
Annual Production | 1,700,000
units
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,948 | 1,537,808 |
kWh
|
$0.032 |
Electricity Demand | $61,395 | 3,960 |
kW-mo/yr
|
$15.50 |
Electricity Fees | $(-1,075.0) | - |
|
- |
Natural Gas | $9,193 | 2,275 |
MMBtu
|
$4.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,311 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,962 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $173 | $157 |
$52
1,758
kWh
|
$121
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,518 | $3,418 |
$438
14,654
kWh
|
$1,080
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7135: Install occupancy sensors | $490 | $500 |
$490
15,826
kWh
|
- | - | - | - | - | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $1,733 | - | - | - |
$1,733
-
MMBtu
|
- | - | - | |
05 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $15,000 | $1,500 | - | - | - | - | - | $15,000 | |
06 | 3.3122: Use filtration, centrifuging to remove contaminants | $1,435 | $4,535 | - | - | - |
$1,435
-
gal
|
- | - | |
07 | 4.431: Train operators for maximum operating efficiency | $1,962 | $200 | - | - | - | - | $1,962 | - | |
TOTAL RECOMMENDED | $22,311 | $10,310 |
$980
32,238
kWh
|
$1,201
-
kW-mo/yr
|
$1,733
-
MMBtu
|
$1,435
-
gal
|
$1,962 | $15,000 | ||
TOTAL IMPLEMENTED | $1,962 | $200 | - | - | - | - | $1,962 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs