ITAC Assessment: UM0103
ITAC logo
ITAC Assessment: UM0103
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Machined Parts
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 58
Plant Area 49,376
ft2
Annual Production 1,700,000
units
Production Hrs. Annual 6,864
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,948 1,537,808
kWh
Electricity Demand $61,395 3,960
kW-mo/yr
Electricity Fees $(-1,075.0) -
Natural Gas $9,193 2,275
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,311 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,962

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4133: Use most efficient type of electric motors $173 $157 $52
1,758
kWh
$121
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,518 $3,418 $438
14,654
kWh
$1,080
-
kW-mo/yr
- - - -
03 2.7135: Install occupancy sensors $490 $500 $490
15,826
kWh
- - - - -
04 2.7221: Lower temperature during the winter season and vice-versa $1,733 - - - $1,733
-
MMBtu
- - -
05 3.5248: Separate and recycle scrap metal to foundry or for sale $15,000 $1,500 - - - - - $15,000
06 3.3122: Use filtration, centrifuging to remove contaminants $1,435 $4,535 - - - $1,435
-
gal
- -
07 4.431: Train operators for maximum operating efficiency $1,962 $200 - - - - $1,962 -
TOTAL RECOMMENDED $22,311 $10,310 $980
32,238
kWh
$1,201
-
kW-mo/yr
$1,733
-
MMBtu
$1,435
-
gal
$1,962 $15,000
TOTAL IMPLEMENTED $1,962 $200 - - - - $1,962 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs