| Assessment Year | 1998 |
|---|---|
| Principal Product | Forged Steel Items |
| NAICS |
n/a
|
| SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
| Sales Range | $5 M to 10M |
| # of Employees | 48 |
| Plant Area |
80,000
ft2
|
| Annual Production | 7,500
ton
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $226,284 | 3,310,082 |
kWh
|
$0.068 |
| Electricity Demand | $97,158 | 6,300 |
kW-mo/yr
|
$15.42 |
| Electricity Fees | $11,498 | - |
|
- |
| Natural Gas | $108,940 | 30,239 |
MMBtu
|
$3.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $48,336 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $763 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $334 | $583 |
$102
2,638
kWh
|
$232
-
kW-mo/yr
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,544 | $5,431 |
$515
13,189
kWh
|
$1,029
-
kW-mo/yr
|
- | - | |
| 03 | 2.7145: Install skylights | $562 | $1,288 |
$562
9,672
kWh
|
- | - | - | |
| 04 | 3.5311: Recover and reuse waste material | $8,280 | $250 | - | - |
$8,280
-
lb
|
- | |
| 05 | 4.431: Train operators for maximum operating efficiency | $429 | $160 | - | - | - | $429 | |
| 06 | 4.513: Re-arrange equipment layout to reduce labor costs | $37,187 | $8,400 | - | - | - | $37,187 | |
| TOTAL RECOMMENDED | $48,336 | $16,112 |
$1,179
25,499
kWh
|
$1,261
-
kW-mo/yr
|
$8,280
-
lb
|
$37,616 | ||
| TOTAL IMPLEMENTED | $763 | $743 |
$102
2,638
kWh
|
$232
-
kW-mo/yr
|
- | $429 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs