Assessment Year | 1997 |
---|---|
Principal Product | Dry Baking Goods |
NAICS |
n/a
|
SIC | 2041: Flour and Other Grain Mill Products |
Sales Range | $50 M to 100M |
# of Employees | 350 |
Plant Area |
262,750
ft2
|
Annual Production | 14,000,000
units
|
Production Hrs. Annual | 6,468
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $269,371 | 7,924,971 |
kWh
|
$0.034 |
Electricity Demand | $340,527 | 39,252 |
kW-mo/yr
|
$8.68 |
Electricity Fees | $(-426,331.0) | - |
|
- |
Natural Gas | $45,272 | 1,919 |
MMBtu
|
$23.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $198,530 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $193,361 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $2,449 | $4,445 |
$1,595
46,893
kWh
|
$854
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,340 | $1,500 |
$3,340
40,445
kWh
|
- | - | - | |
03 | 2.3132: Recharge batteries on during off-peak demand periods | $4,254 | $2,400 | - |
$4,254
-
kW-mo/yr
|
- | - | |
04 | 3.4151: Minimize water usage | $915 | - | - | - |
$915
-
Tgal
|
- | |
05 | 4.441: Install automatic packing equipment | $187,572 | $28,169 | - | - | - | $187,572 | |
TOTAL RECOMMENDED | $198,530 | $36,514 |
$4,935
87,338
kWh
|
$5,108
-
kW-mo/yr
|
$915
-
Tgal
|
$187,572 | ||
TOTAL IMPLEMENTED | $193,361 | $34,114 |
$4,935
87,338
kWh
|
$854
-
kW-mo/yr
|
- | $187,572 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs