Assessment Year | 1997 |
---|---|
Principal Product | Reels and Mandrels |
NAICS |
n/a
|
SIC | 3547: Rolling Mill Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 155 |
Plant Area |
104,800
ft2
|
Annual Production | 216,000
units
|
Production Hrs. Annual | 6,321
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $137,553 | 2,807,737 |
kWh
|
$0.049 |
Electricity Demand | $87,357 | 5,064 |
kW-mo/yr
|
$17.25 |
Electricity Fees | $51,136 | - |
|
- |
Natural Gas | $24,370 | 17,868 |
MMBtu
|
$1.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,947 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,107 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,423 | $1,650 |
$773
17,585
kWh
|
$650
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,152 | $10,210 |
$1,699
38,687
kWh
|
$2,453
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $373 | $600 |
$252
6,155
kWh
|
$121
-
kW-mo/yr
|
- | - | |
04 | 2.7135: Install occupancy sensors | $688 | $400 |
$688
17,292
kWh
|
- | - | - | |
05 | 3.4111: Use closed cycle process to minimize waste water production | $3,511 | $3,500 | - | - |
$3,511
-
Tgal
|
- | |
06 | 4.511: Expand operations into unused space | $6,800 | $400 | - | - | - | $6,800 | |
TOTAL RECOMMENDED | $16,947 | $16,760 |
$3,412
79,719
kWh
|
$3,224
-
kW-mo/yr
|
$3,511
-
Tgal
|
$6,800 | ||
TOTAL IMPLEMENTED | $12,107 | $6,150 |
$1,025
23,740
kWh
|
$771
-
kW-mo/yr
|
$3,511
-
Tgal
|
$6,800 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs