| Assessment Year | 1997 |
|---|---|
| Principal Product | Steering Components |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 144 |
| Plant Area |
75,251
ft2
|
| Annual Production | 500,000
pieces
|
| Production Hrs. Annual | 4,040
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $42,807 | 1,446,366 |
kWh
|
$0.030 |
| Electricity Demand | $71,561 | 4,248 |
kW-mo/yr
|
$16.85 |
| Electricity Fees | $1,333 | - |
|
- |
| Natural Gas | $71,099 | 7,110 |
MMBtu
|
$10.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $138,617 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $570 | $907 |
$243
8,206
kWh
|
$327
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,163 | $5,109 |
$735
24,912
kWh
|
$1,428
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,967 | $600 |
$1,265
42,790
kWh
|
$1,702
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $1,420 | $4,000 | - | - |
$1,420
-
MMBtu
|
- | - | |
| 05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $10,164 | - | - | - | - |
$10,164
-
lb
|
- | |
| 06 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $108,607 | - | - | - | - |
$108,607
-
lb
|
- | |
| 07 | 4.321: Optimize production lot sizes and inventories | $12,726 | - | - | - | - | - | $12,726 | |
| TOTAL RECOMMENDED | $138,617 | $10,616 |
$2,243
75,908
kWh
|
$3,457
-
kW-mo/yr
|
$1,420
-
MMBtu
|
$118,771
-
lb
|
$12,726 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs