ITAC Assessment: UM0082
ITAC logo
ITAC Assessment: UM0082
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Airline Meals/Beverages
NAICS
n/a
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 585
Plant Area 20,000
ft2
Annual Production 6,570,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $133,349 5,443,728
kWh
Electricity Demand $142,985 9,228
kW-mo/yr
Electricity Fees $5,220 -
Natural Gas $145,437 34,060
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $132,711 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $120,892

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Product Savings
01 2.4133: Use most efficient type of electric motors $5,892 $5,190 $3,502
118,699
kWh
$2,390
-
kW-mo/yr
- - -
02 2.2414: Use waste heat from hot flue gases to preheat $5,427 $3,920 - - $5,427
-
MMBtu
- -
03 2.2437: Recover waste heat from equipment $5,039 $6,000 - - $5,039
-
MMBtu
- -
04 3.5212: Regrind, reuse, or sell scrap plastic parts $1,353 $3,800 - - - $1,353
-
lb
-
05 4.514: Re-arrange equipment layout to reduce handling costs $115,000 $2,400 - - - - $115,000
TOTAL RECOMMENDED $132,711 $21,310 $3,502
118,699
kWh
$2,390
-
kW-mo/yr
$10,466
-
MMBtu
$1,353
-
lb
$115,000
TOTAL IMPLEMENTED $120,892 $7,590 $3,502
118,699
kWh
$2,390
-
kW-mo/yr
- - $115,000
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs