Assessment Year | 1996 |
---|---|
Principal Product | Aluminum Die Castings |
NAICS |
n/a
|
SIC | 3363: Aluminum Die-Castings |
Sales Range | $10 M to 50M |
# of Employees | 89 |
Plant Area |
32,500
ft2
|
Annual Production | 7,800,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $115,632 | 3,854,631 |
kWh
|
$0.030 |
Electricity Demand | $80,986 | 6,696 |
kW-mo/yr
|
$12.09 |
Electricity Fees | $8,319 | - |
|
- |
Natural Gas | $47,700 | 38,922 |
MMBtu
|
$1.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,325 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,346 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,500 | $1,607 |
$1,018
29,015
kWh
|
$482
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,561 | $12,818 |
$2,681
50,703
kWh
|
$880
-
kW-mo/yr
|
- | - | |
03 | 2.3212: Optimize plant power factor | $2,418 | $6,182 | - | - | $2,418 | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,807 | $2,550 |
$1,226
34,877
kWh
|
$581
-
kW-mo/yr
|
- | - | |
05 | 3.4113: Treat and reuse rinse waters | $1,039 | $1,000 | - | - | - |
$1,039
-
Tgal
|
|
TOTAL RECOMMENDED | $10,325 | $24,157 |
$4,925
114,595
kWh
|
$1,943
-
kW-mo/yr
|
$2,418 |
$1,039
-
Tgal
|
||
TOTAL IMPLEMENTED | $4,346 | $5,157 |
$2,244
63,892
kWh
|
$1,063
-
kW-mo/yr
|
- |
$1,039
-
Tgal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs