| Assessment Year | 1996 |
|---|---|
| Principal Product | Heat Treating Services |
| NAICS |
n/a
|
| SIC | 3398: Metal Heat Treating |
| Sales Range | $5 M to 10M |
| # of Employees | 80 |
| Plant Area |
33,971
ft2
|
| Annual Production | 120,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $66,820 | 2,443,728 |
kWh
|
$0.027 |
| Electricity Demand | $82,373 | 4,961 |
kW-mo/yr
|
$16.60 |
| Natural Gas | $385,813 | 147,782 |
MMBtu
|
$2.61 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $58,108 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $1,740 | $1,524 | n/a |
$1,070
16,999
kWh
|
$670
-
kW-mo/yr
|
- | - | - |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,191 | - | n/a |
$1,965
31,360
kWh
|
$1,226
-
kW-mo/yr
|
- | - | - |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,196 | $16,857 | n/a |
$15,296
244,138
kWh
|
$5,900
-
kW-mo/yr
|
- | - | - |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $12,905 | $18,590 | n/a | - | - |
$12,905
-
MMBtu
|
- | - |
| 05 | 3.3133: Use other waste concentration methods | $10,494 | $38,000 | n/a | - | - | - |
$1,568
-
lb
|
$8,926 |
| 06 | 3.1182: Make a new by-product | $8,582 | - | n/a | - | - | - |
$8,582
-
lb
|
- |
| TOTAL RECOMMENDED | $58,108 | $74,971 |
$18,331
292,497
kWh
|
$7,796
-
kW-mo/yr
|
$12,905
-
MMBtu
|
$10,150
-
lb
|
$8,926 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs