ITAC Assessment: UM0039
ITAC logo
ITAC Assessment: UM0039
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Metal heat Treating
NAICS
n/a
SIC 3398: Metal Heat Treating
Sales Range $1
M
to 5
M
# of Employees 44
Plant Area 10,000
ft2
Annual Production 265,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,484 1,320,926
kWh
Natural Gas $147,064 45,431
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,643 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,965

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $1,253 $655 $1,253
22,274
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $555 $1,453 $555
9,965
kWh
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,157 $350 $1,157
20,516
kWh
-
04 2.2427: Use waste heat from hot flue gases to preheat incoming fluids $3,678 $1,832 - $3,678
-
MMBtu
TOTAL RECOMMENDED $6,643 $4,290 $2,965
52,755
kWh
$3,678
-
MMBtu
TOTAL IMPLEMENTED $2,965 $2,458 $2,965
52,755
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs