ITAC Assessment: UM0036
ITAC logo
ITAC Assessment: UM0036
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Stampings
NAICS
n/a
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 40,000
ft2
Annual Production 10,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $90,628 901,524
kWh
Natural Gas $17,271 4,365
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,168 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,168

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $5,067 $5,500 $5,067
50,117
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,841 $3,216 $1,841
18,171
kWh
- -
03 2.8114: Change rate schedules or other changes in utility service $9,936 $250 - - $9,936
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,177 $300 $4,177
41,325
kWh
- -
05 2.7243: Improve air circulation with destratification fans / other methods $6,147 $5,600 - $6,147
-
MMBtu
-
TOTAL RECOMMENDED $27,168 $14,866 $11,085
109,613
kWh
$6,147
-
MMBtu
$9,936
TOTAL IMPLEMENTED $27,168 $14,866 $11,085
109,613
kWh
$6,147
-
MMBtu
$9,936
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs